To ensure maximum efficiency and optimal performance of engines, OES has successfully completed the overhaul of two Waukesha Gas Engines at Pakistan Petroleum Limited Adhi Field in Gujjar Khan.
This critical project, vital for maintaining the natural gas supply, had to be completed within a demanding 72-hour (3-day) deadline set by the customer. Although OES routinely performs overhauls of Waukesha engines, this task was uniquely challenging as it required back-to-back top overhauls (TOH) of two engines, necessitating exceptional time management and technical expertise.
Despite these constraints, OES successfully delivered the project on time, restoring the engines to full operation and ensuring uninterrupted gas supply. This achievement highlights our unwavering commitment to high-quality service, even under pressure and completion of time-sensitive projects with precision.